RAIL PASSENGER INFORMATION & SURVEILLANCE

PAPIS / CCTV Renewal for TCDD HT65000 Fleet

Renewal of the on-board passenger information, in-train entertainment and CCTV surveillance systems on TCDD HT65000 high-speed trains with an integrated, IP-based, EN 50155-compliant solution; planning started in 2024, the first train is delivered to TCDD and the second train is currently under test, with the rest of the fleet to follow.

OngoingTürkiye
PAPIS / CCTV Renewal for TCDD HT65000 Fleet

Project Overview

Renewal of the on-board passenger information, in-train entertainment and CCTV surveillance systems on TCDD HT65000 high-speed trains with an integrated, IP-based, EN 50155-compliant solution; planning started in 2024, the first train is delivered to TCDD and the second train is currently under test, with the rest of the fleet to follow.

Planck Signaling is renewing the on-board Passenger Information (PAPIS), in-train entertainment and CCTV surveillance systems on TCDD HT65000 high-speed trains with an integrated, IP-based solution. The project is one of our most strategic engagements: it covers the entire HT65000 fleet, train by train, and replaces ageing PIS and CCTV equipment with EN 50155-compliant devices designed for the demanding rail environment.

The integrated system combines location-based automatic announcements, passenger information on TFT and seat-back displays, in-train entertainment and CCTV surveillance over a single IP backbone — so audio, video, signage and security run on the same network with consistent management and diagnostics. Planning started in 2024; the first train has been delivered to TCDD, the second train is currently under acceptance testing and the remaining HT65000 sets will be renewed in the following phases.

Project Highlights

  • FLEETTCDD HT65000 high-speed trains
  • ARCHITECTUREIntegrated IP-based PIS, entertainment & CCTV
  • STANDARDSEN 50155-compliant on-board equipment
  • ANNOUNCEMENTSLocation-based automatic announcements
  • PASSENGER DISPLAYSTFT signage & seat-back screens
  • SURVEILLANCE & ENTERTAINMENTOn-board CCTV and in-train entertainment
  • CUSTOMER / OPERATORTCDD Taşımacılık

Project Timeline

Q1 2024

Planning & Scoping

Fleet-wide renewal plan defined with TCDD for HT65000 PAPIS, in-train entertainment and CCTV; per-train scope and rollout sequence agreed.

Q2 2024

System Design

Integrated IP-based architecture designed; EN 50155-compliant equipment selected, network topology, TFT/seat-back display layout and CCTV coverage defined.

Q3 2024 – Q3 2025

Procurement & Software

Extended phase covering procurement of PAPIS, entertainment and CCTV hardware together with development, configuration and integration of location-based announcement, signage and surveillance software.

Q4 2025

First Train — Installation

First HT65000 set fully fitted with the new integrated PAPIS, in-train entertainment and CCTV system in Q4 2025; cabling, displays and CCTV cameras deployed.

Q1 2026

First Train — Tests & Delivery

Acceptance tests completed on the first HT65000 set; train delivered to TCDD and put into service with the renewed system.

Q1 – Q2 2026

Second Train — Installation

Second HT65000 set fitted with the integrated PAPIS, entertainment and CCTV system following the validated first-train configuration.

Q2 2026 →

Second Train — Tests in Progress

Acceptance tests of the second HT65000 set are currently in progress; once validated, the train will be delivered to TCDD.

TBD

Remaining Fleet — Rollout

Remaining HT65000 sets to be renewed in the following phases until the entire fleet's PAPIS, in-train entertainment and CCTV systems are upgraded.

Our Projects