Gaziray ETCS Level 1 & 2 On-Board Installation

Installation of HollySys on-board ETCS Level 1 and Level 2 equipment on 4-car trains for the Gaziantep commuter line (Gaziray), with 2 on-board units fitted per train across the prototype and serial-production fleet.

OngoingSakarya, Türkiye
Gaziray ETCS Level 1 & 2 On-Board Installation

Project Overview

Installation of HollySys on-board ETCS Level 1 and Level 2 equipment on 4-car trains for the Gaziantep commuter line (Gaziray), with 2 on-board units fitted per train across the prototype and serial-production fleet.

Planck Signaling supplied and installed HollySys on-board ETCS Level 1 and Level 2 equipment for the Gaziantep commuter rail line (Gaziray). The installation work was carried out in Sakarya on 4-car commuter trains, with 2 on-board units fitted on each train.

The scope covers one prototype train (2 on-board systems) and the serial-production fleet of 8 trains (16 on-board systems), for a total of 18 on-board ETCS installations. The end customer is Gaziantep Metropolitan Municipality, with TÜRASAŞ acting as the train operator/authority. Planck Signaling is responsible for sourcing the HollySys equipment as their local partner and for installing the systems on the vehicles.

Project Highlights

  • FLEET1 prototype + 8 serial trains
  • SYSTEMETCS Level 1 & Level 2 on-board
  • ON-BOARD UNITS18 systems (2 per train)
  • OPERATORTÜRASAŞ
  • CUSTOMERGaziantep Metropolitan Municipality

Project Timeline

PROTOTYPE TRAIN

Q1 2024

Planning

Project engineering and planning for the prototype on-board installation.

Q3 2024

Procurement

HollySys ETCS on-board equipment sourced and delivered to site.

Q4 2024

Installation

Two on-board units installed on the prototype train in Sakarya.

Q2 2025

Testing

Functional and integration tests completed on the prototype train.

SERIAL PRODUCTION

Q1 2025

Planning

Engineering and planning for the serial fleet of eight trains.

Q3 2025

Procurement

Serial production hardware procured from HollySys.

Q3 – Q4 2025

Installation

Two on-board ETCS units installed on each of the eight serial-production trains.

Q1 2026

Roll-out Completion

Full fleet installation completed and handed over for commissioning.

TBD

Final Tests

Final acceptance test dates are being finalised.